ARJ Transforms Aldenham School in just 7 weeks

Following meticulous planning and extensive surveys, ARJ have transformed the boys accommodation at Aldenham School in just seven weeks.
Surveys and planning started five weeks before works on-site, as little as-built information was available. Every pipe, cable, duct, switch and wall had to be surveyed to ensure existing systems remained operational. Once surveying was complete, works started on site at full speed. Seven weeks later the transformation was complete.

“ARJ successfully completed this sizeable project within a tight timescale enabling the School to open these Boarding Houses on time at the start of term. The commitment of the on site management and their organisation of the workforce and their interface with the School was of a high standard throughout the project”.

Andrew Fraser
Bursar & Clerk to the Governors, The Aldenham Foundation

>> More Information

Latest News

IMG_6840 (+sky CB) REDUCED

Innova Apartments Complete

26th April 2019
Read Article...
Brochure_Page_02_Image_0001

ARJ Delivering Apt Kew Bridge

16th April 2019
Read Article...
IMG_5661 reduced

Kisharon School Topping Out

2nd April 2019
Read Article...
We use cookies, just to track visits to our website, we store no personal details. Close